Davison Day Nursery Extension Timeline

August 2019


The builders worked hard over the summer holidays and the Pre-School room is ready for us to use. There are a few finishing touches to be completed and photos will follow soon.




July 2019


We have a roof!

Insulation is now complete and walls to the office and store have been formed. Walls have been plaster boarded and plaster skimmed. Look out for the final stage and landscaping of the garden.





June 2019


Latest photo...We now have the beginnings of a roof.



June 2019


This week has seen the fabrication and erecting of the timber frame which has been successful. The roof trusses will be delivered on Monday 24th and scaffolding is going up this Saturday, it is anticipated that the trusses will be fully assembled and braced by Monday evening. The roofers will start the felt and battening by the end of next week. Watch this space.....




May 2019


During May half term the block and beam flooring was laid.




April 2019


The first stage of the extension took place during the Easter holidays. The foundations were laid and the area is fenced off for the time being.